Bannerman Newsletter | NO 3 | MAY 2024

Welcome to interactive presentation, created with Publuu. Enjoy the reading!

Scoping Study

BANNERMAN

MINING RESOURCES NAMIBIA

Omasa is the newsletter for the Etango Uranium Project managed by the following companies:

We want to hear from you!

Omasa

Omasa intends to keep you informed about progress on the Etango Uranium Project,

intends to keep you informed about progress on the Etango Uranium Project,

its people and its activities. What else would you like to read more about?

its people and its activities. What else would you like to read more about?

Send your comments, compliments and suggestions to:

Send your comments, compliments and suggestions to:

Emma Culver: newsletters@bmnenergy.com.

Editorial team: Gavin Chamberlain, Emma Culver

Gavin Chamberlain, Emma Culver Production: Words’Worth

Words’Worth

Construction Update

wo important steps towards constructing the Etango Project have

wo important steps towards constructing the Etango Project have

been taken. “The early works contracts for the Etango temporary

been taken. “The early works contracts for the Etango temporary

water pipeline and the access road were placed in December 2023 and

water pipeline and the access road were placed in December 2023 and

construction works were commissioned at the end of January 2024,” informs

construction works were commissioned at the end of January 2024,” informs

Andre Alberts, Technical Project Manager at Bannerman Mining Resources

Andre Alberts, Technical Project Manager at Bannerman Mining Resources

Namibia.

Namibia.

Namibbeton, a local Namibian contractor, is the appointed contractor with

Namibbeton, a local Namibian contractor, is the appointed contractor with

construction supervision being done by Creo Engineering Solutions.

construction supervision being done by Creo Engineering Solutions.

Water pipeline

The temporary water pipeline installation covers a 24km stretch from the

The temporary water pipeline installation covers a 24km stretch from the

B2 down to the Swakop River valley and up to the Etango site. It will mostly

B2 down to the Swakop River valley and up to the Etango site. It will mostly

run underground and consists of High Density Polyethylene (HDPE) pipe

run underground and consists of High Density Polyethylene (HDPE) pipe

sections welded together and will terminate at a steel reservoir on site.

sections welded together and will terminate at a steel reservoir on site.

“This pipeline will ensure that all construction work on site for building

“This pipeline will ensure that all construction work on site for building

the processing plant can continue while the permanent water pipeline will

the processing plant can continue while the permanent water pipeline will

be constructed,” says Andre. “Installation of the first half of the pipeline is

be constructed,” says Andre. “Installation of the first half of the pipeline is

complete and the first performance testing took place in April. Completion

complete and the first performance testing took place in April. Completion

of the pipeline installation is planned for end of July 2024 and is well on

of the pipeline installation is planned for end of July 2024 and is well on

track.”

track.”

Access road

An access road consisting of a 4km engineered gravel road will connect the

An access road consisting of a 4km engineered gravel road will connect the

Etango site to the C28 road. Materials for construction are being borrowed

Etango site to the C28 road. Materials for construction are being borrowed

from selected sites on the Etango mining license. The roadbed and cut-to-fill

from selected sites on the Etango mining license. The roadbed and cut-to-fill

work has been completed, with the subbase and base layers installed. The

work has been completed, with the subbase and base layers installed. The

road construction work is on track to meet the completion deadline of end-

road construction work is on track to meet the completion deadline of end-

May 2024.

May 2024.

“Meeting the Environmental and Social Impact Assessment’s guidelines

“Meeting the Environmental and Social Impact Assessment’s guidelines

and requirements has been a key focus for all stakeholders involved,” says

and requirements has been a key focus for all stakeholders involved,” says

Andre. This includes a careful exercise of locating and demarcating sensitive

Andre. This includes a careful exercise of locating and demarcating sensitive

environmental and archaeological areas.

environmental and archaeological areas.

“Successfully executing the works without any lost-time injuries is a

“Successfully executing the works without any lost-time injuries is a

testimony of Bannerman’s high safety standards.” Andre attributes this to

testimony of Bannerman’s high safety standards.” Andre attributes this to

good collaboration between the Bannerman team, Creo, and Namibbeton.

good collaboration between the Bannerman team, Creo, and Namibbeton.

The construction water pipeline is positioned.

Andre Alberts, Technical Project Manager at Bannerman Mining Resources Namibia

BUILDING A GIANT

FROM THE GROUND UP

Length of temporary

water pipeline

Lost-time injuries

on site

Length of access

gravel road

Completion of the

pipeline installation

24 km

4 km

Zero

July 2024

We can go higher and longer (cont)

Key Physical Parameters: Etango-8, -XP and -XT Projects

Key Physical Parameters

Etango-8

Etango-XP

Etango-XT

Life of Mine U

Life of Mine U3O8 output:

output:

52.6 Mlbs over 15 years

52.6 Mlbs over 15 years

95.2 Mlbs over 16 years

95.2 Mlbs over 16 years

95.2 Mlbs over 27 years

95.2 Mlbs over 27 years

Annual average U

Annual average U3O8 output:

output:

3.5 Mlbs

3.5 Mlbs

6.7 Mlbs (after plant expansion)

6.7 Mlbs (after plant expansion)

3.5 Mlbs

3.5 Mlbs

Expansion capex:

Expansion capex:

US$ 0

US$ 0

US$ 325 million

US$ 325 million

US$ 0

US$ 0

Sustaining cash cost:

Sustaining cash cost:

US$ 38.1/lb of U

US$ 38.1/lb of U3O8

US$ 42.5/lb of U

US$ 42.5/lb of U3O8

US$ 45.3/lb of U

US$ 45.3/lb of U3O8

THE MAN WHO HAS STUDIED IT ALL

erner Moeller, Director of Qubeka Mining

erner Moeller, Director of Qubeka Mining

Consultants, has had a 15-year association

Consultants, has had a 15-year association

with the Etango Project, taking it through the

with the Etango Project, taking it through the

different study phases of the 8 Mtpa business

different study phases of the 8 Mtpa business

case and optimising it to advance Etango to the

case and optimising it to advance Etango to the

construction stage.

construction stage.

“Towards the end of 2023 we started evaluating

“Towards the end of 2023 we started evaluating

potential life-of-mine extension scenarios from

potential life-of-mine extension scenarios from

the current 15 years by increasing the Etango

the current 15 years by increasing the Etango

Project’s plant throughput to 16 Mtpa. From

Project’s plant throughput to 16 Mtpa. From

a mining engineering perspective, I ran and

a mining engineering perspective, I ran and

evaluated the different production schedule

evaluated the different production schedule

BANNERMAN ENERGY | MAY 2024

scenarios.” This culminated in two alternate

scenarios.” This culminated in two alternate

future expansion options for the XP and XT

future expansion options for the XP and XT

Scoping Study to the current Etango-8 Mtpa

Scoping Study to the current Etango-8 Mtpa

Project.

Project.

“We are delighted with the XP and XT

“We are delighted with the XP and XT

Scoping Study results, which demonstrate

Scoping Study results, which demonstrate

that Etango is a long-life, low-cost and

that Etango is a long-life, low-cost and

economically robust open pit uranium project

economically robust open pit uranium project

with significant upside. It is geologically

with significant upside. It is geologically

consistent, metallurgically simple and

consistent, metallurgically simple and

technically low risk with a low capital intensity

technically low risk with a low capital intensity

and significant future upside.”

and significant future upside.”

LOOK WHO’S BLOWING

OUT CANDLES

The following celebrate their

birthdays in the coming weeks.

MAY

• Emma Culver, Communications Coordinator

• Alison Terry, Non-Executive Director

•• Werner Ewald, Managing Director

JULY

• Steve Herlihy, Chief Financial Officer

•• Imelda Naobes, Office Administrator

• Bannerman Energy Ltd (Australia)

•• Bannerman Mining Resources Namibia

LEGEND